Healthcare
Regional Medical Center Tower
Location
Columbus, OH
Duration
14 months
Duration
14 months
Year
2023
Year
2023
Market Size
180,000 SF
Client
Aria Build
Crew
28
Crew
28
Delivery Method
Construction Management at Risk
Delivery Method
Construction Management at Risk
Capability
Commissioning
Capability
Commissioning
THE CHALLENGE
Delivering a new central utility plant and life-safety power distribution into a live hospital campus — with utility tie-ins requiring coordinated shutdowns in an occupied, 24/7 facility.


OUR APPROACH
Northgrid developed a detailed outage sequence with the owner’s facilities group and the GC, executing each tie-in during low-census windows with fully staged temporary power in place throughout.
RESULTS
All 14 utility tie-ins were completed without an unplanned outage. The project delivered two weeks ahead of schedule and exceeded the owner’s uptime protection requirements for the duration of construction.



Healthcare
Regional Medical Center Tower
Location
Columbus, OH
Duration
14 months
Year
2023
Market Size
180,000 SF
Client
Aria Build
Crew
28
Delivery Method
Construction Management at Risk
Capability
Commissioning
THE CHALLENGE
Delivering a new central utility plant and life-safety power distribution into a live hospital campus — with utility tie-ins requiring coordinated shutdowns in an occupied, 24/7 facility.


OUR APPROACH
Northgrid developed a detailed outage sequence with the owner’s facilities group and the GC, executing each tie-in during low-census windows with fully staged temporary power in place throughout.
RESULTS
All 14 utility tie-ins were completed without an unplanned outage. The project delivered two weeks ahead of schedule and exceeded the owner’s uptime protection requirements for the duration of construction.