Federal & defense
Colocation Build-to-Suit
Location
Dallas, TX
Duration
7 months
Duration
7 months
Year
2024
Year
2024
Market Size
140,000 SF
Client
Northpeak GC
Crew
22
Crew
22
Delivery Method
Design-Bid-Build / Fast-Track
Delivery Method
Design-Bid-Build / Fast-Track
Capability
Fire protection
Capability
Fire protection
THE CHALLENGE
Compressing a standard 12-month electrical and mechanical scope into a 7-month schedule to meet a tenant move-in commitment tied to a capital lease obligation.


OUR APPROACH
Northgrid used its prefab program aggressively — fabricating and testing switchgear lineups and chilled-water distribution skids in its Dallas facility while site civil and structural work was still in progress.
RESULTS
Substantial completion was achieved on the 7-month schedule. The tenant’s IT equipment was on-site within 72 hours of final commissioning acceptance, and the build earned a repeat engagement for Phase II.



Federal & defense
Colocation Build-to-Suit
Location
Dallas, TX
Duration
7 months
Year
2024
Market Size
140,000 SF
Client
Northpeak GC
Crew
22
Delivery Method
Design-Bid-Build / Fast-Track
Capability
Fire protection
THE CHALLENGE
Compressing a standard 12-month electrical and mechanical scope into a 7-month schedule to meet a tenant move-in commitment tied to a capital lease obligation.


OUR APPROACH
Northgrid used its prefab program aggressively — fabricating and testing switchgear lineups and chilled-water distribution skids in its Dallas facility while site civil and structural work was still in progress.
RESULTS
Substantial completion was achieved on the 7-month schedule. The tenant’s IT equipment was on-site within 72 hours of final commissioning acceptance, and the build earned a repeat engagement for Phase II.